
|
|
|
|
Schemes of over 50MW capacity - even if they would only produce a fraction of this amount in operation - are submitted to for determination by a Minister according to Section 36 of the Electricity Act 1989 (or the equivalent Section 57 of the Town and Country Planning (Scotland) Act 1997). This was originally intended as a mechanism for major projects that were considered to be in the national interest. It is questionable whether it was intended as a mechanism for developers to sideline the local planning process with wind power projects having a theoretical maximum capacity of just over 50MW, and which would produce as little as 20% to 30% of that headline capacity in operation.
Some developers regard Section 36 applications as standing more chance - they are, after all, being decided by a Minister who is also responsible for implementing current energy policy - than would smaller schemes with local planners who are more inclined to reflect the concerns of their local communities and the local economy. A public inquiry can be triggered by the formal objection of a local planning authority, but the developers know very well that cash-strapped local authorities and poorly funded community groups are then forced to find large sums of money in order to secure legal representation. At the end of the day, the Secretary of State can, but seldom does, override an inspector's recommendation.
Peak theoretical capacity figures are given for turbines and sites. The intermittent nature of wind power means that the capacity or load factor of wind turbines can be anything between 8% and 40% of the headline figure, depending on the wind resource on site. The BWEA likes to claim that onshore wind turbine arrays usually have a capacity factor of 30%; our regional planners assume a figure of 29/30%. The March 2006 issue of 'Energy Trends', produced by the Department of Trade and Industry, has a table of capacity, or load, factors for onshore wind farms in the UK produced from actual production figures. This table shows that the North East has the lowest recorded load factor in the country: for 2003 the figure was 19%; for 2004 the figure was 21%. The average for 1998-2004 was 21%.
We are now including some output and load factor figures taken from Ofgem's data (lack of figures signals that a full year's production did not take place). This data is published in more accessible form by REF as a PDF download. (See 'UK Renewable Energy Data').
‘Scoping’ = site investigation, pre-application consultation with planning authority (may involve application to erect an anemometer mast for recording wind speeds, not required by the planning process but needed when raising finance).
‘Live Application’ = planning application submitted.
‘Appealed’ = proposals may be appealed by the applicant after refusal or for ‘non-determination’, when the applicant decides to trigger an appeal
because the local planning authority has not determined the application within the prescribed time period (normally 12 weeks). Objectors have no right of appeal if a decision is approved, they can only seek to overturn the decision by going to the High Court (in England) to seek a judicial review of the decision on procedural grounds. This rarely succeeds and can be ruinously expensive if costs are awarded to the company.
‘Called in/Recovered’ = decision removed from a Planning Inspector to the Secretary of State, or Scottish equivalent. There are a number of reasons set out for this action, the English government has recently started recovering decisions because, “the appeal involves proposals of major significance for the delivery of the Government's climate change programme and energy policies.”
‘PI’ = Public Inquiry; hearing to publically examine the application in a quasi-judicial hearing before a Planning Inspector (‘Reporter’ in Scotland).
‘Status unclear’ = lapsed, withdrawn, not proceeding etc.
‘LF’ = Load Factor: percentage of headline capacity produced by turbine(s), averaged over a year.
‘NYD’ = Not yet determined.
‘TIGC’ = Total Installed Generating Capacity.
Rejected and lapsed/withdrawn proposals are included below because, even after failure at appeal, they can reappear as slightly adjusted re-submissions. Some developers are notoriousy unwilling to take no for an answer when they have spent some money in working up a proposal. These sites also indicate areas of developer interest.
Title colours match application status: orange - scoping/pre-planning; red - in planning (applied/appealed); green - approved; black - operating; grey - refused, withdrawn, lapsed etc.
|
|
|
|
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Aesica Pharmaceuticals | Cramlington | 2 | 110m. | 2.5MW | 5MW | Refused. Appeal withdrawn. |
Applied 5/06 for two 140m turbines (06/00275/ful). Rejected 15.8.06, radar impacts (Newcastle Airport). Re-applied 8/06, two 110m turbines (06/00384/res). Permission refused. Appeal lodged, withdrawn before the hearing. |
|
| Barmoor | Nr. Lowick (NT980380) |
6 | 110.5m. | 3MW | 18MW | Catamount/ Force 9 |
Approved on appeal | Refused by LPA (27/03/08). Appeal heard (May-June 2009). Approved, on Inspector’s recommendation, 20/01/10. SOUL. |
| ‘Berwick’ | ca. 1.5 km. N. of Halidon Hill | 7 | ?120m. | 2MW | 14MW | RES (not listed on website) |
Scoping | |
| Berwick - Ramparts Business Park | Steps of Grace, north of Ramparts Business Park (NT 986555). | 1 | 74m. | 0.8MW | 0.8MW | Community Renewable Energy Ltd | Scoping | Enercon E48 turbine proposed; 50m anemometer erected on the site in May 2008. Income would be shared between Berwick Community Trust and CoRE. |
| 'Bewick Drift' | Lynemouth | 3 | 110m. | 3MW | 9MW | Harworth Power | Approved on appeal (02/08) | |
| Bewick Moor | "2.9 km. SE of Chillingham" | EHN UK | Scoping Mast (Dec. 2005) |
|||||
| Bewick Moor | "3.8 km. NE of Old Bewick" | EHN UK | Scoping Mast (Dec. 2005) |
|||||
| Blyth Harbour | Blyth | 9 | 42.5m. | 0.3MW | 2.7MW | AMEC | Operating (1993) | WindMaster turbines. Repowering, see below.
2002 ROC's/MWh:1,953 2003 ROC's/MWh:2,839; LF:12.0% 2004 ROC's/MWh:2,742; LF:11.6% 2005 ROC's/MWh:3,131; LF:13.2% 2006 ROC's/MWh:2,492; LF:10.5% 2007 ROC's/MWh:2,264; LF:9.6% 2008 ROC's/MWh:1,874; LF:7.9 |
| Blyth Harbour (Repowering) |
Blyth | 7 | 6 x 125m. 1 x 163m. |
6 x 3MW 1 x 5MW |
23MW | Hainsford Energy | Consented (08.01.08) |
An Article 14 hold on the decision pending a decision on whether to hold a PI on radar issues lifted July 2008. 5MW turbine would be largest in UK. |
| Blyth Offshore | Nr. Blyth | 2 | 93m. | 2MW | 4MW | Project Consortium. Sold to E.ON UK June 2007. |
Commissioned 2000. Inoperative 04.06 - 01.09 |
'Demonstration project' built with unspecified financial support from the EU Thermie Programme.
Blade accident on WTG 1, Jan. 2002. ROC's only claimed on WTG 2. Out of service from April 2006 until January 2009 (cable damage). 2002 ROC's/MWh:1,925 2003 ROC's/MWh:2,557; LF:16.2% 2004 ROC's/MWh:4,181; LF:26.5% 2005 ROC's/MWh:1,385; LF:8.8% 2006 ROC's/MWh:337; LF:2.1% 2007 ROC's/MWh:0; LF:0% 2008 ROC's/MWh:0; LF:0% |
| Blyth Offshore 2 | Nr. Blyth | 1 | 163m. | 7.5MW | 7.5MW | Crown Estates | Scoping | Largest turbine proposed in UK.
Will use a ‘Project Britannia’ turbine, in development at Blyth. Questions have been raised about engineering problems with CW’s onshore turbines, their lack of offshore engineering experience and poor financial performance. It was recently reported (30 September, 2009) in The Telegraph that, “Clipper Windpower is in talks with industrial rivals and financial investors about selling a ‘substantial’ stake after making a $120m (£75m) half-year loss”. See also: The Times, 8 Nov. 2009. |
| Boundary Lane | Nr. Whittonstall | 3 | 110m | 2MW | 6MW | Wind Prospect. | Live application (16/06/2009) | |
| Butterwell/Bluberry Wood |
Nr. Longhirst | 9 | 125m. | 2.3MW | 20.7MW | RES, not on website | Proposal announced. | Next to Novera’s Longhirst proposal. Then LPA rejected Anem. Mast application (3/06), approved for 3 yrs.on appeal (12/06). |
| Coat Yards Farm | Nr. Longhorsley | 5 | 125m. | 3MW | 15MW | Coronation Power | 'Dropped after scoping' (NCC) | |
| Currock Hill/Hedley-on-the-Hill | Nr. Hedley-on-the-Hill | 6 (2x3) |
140m. | ? | ? | Pure Renewable Energy | Scoping | See Hexham Courant 25.01.08 |
| Debdon Farm | Nr. Rothbury | 8 | ? | 3MW | 24MW | West Coast Energy Limited. | Mast rejected. |
Anem. Mast refused 8/07 (‘visually intrusive’). |
| Defra Headquarters, Alnwick | Lion House, Alnwick | 3 | 15m | 0.15MW | 0.45MW | Operating | ‘Defra’s green office’. No (public) expense spared demonstration project, poor site for wind power generation. The achieved load factors will be worth seeing. |
|
| Gapshield | Nr. Greenhead | 5 | ? | 2.1MW | 10.5MW | RES (not listed on website) |
Scoping | |
| Green Rigg | Nr. Sweethope Lough | 18 | 110m. | 2MW | 36MW | Wind Prospect | PI held decision awaited |
Joint public inquiry (+ Ray & Steadings) closed 18 Dec. 2008, decision awaited. CREDIT - Campaign for Responsible Energy Development In Tynedale |
| Kielder | Kielder | Unclear | Still described as ‘strategic resource area’ in some circles. Talks ongoing (?) with MOD on radar constraints. |
|||||
| Kielder (Humble Hill) |
Kielder | (100) | (80m.) | (EcoGen) | DTI (DBERR) Refusal (MOD objected) Upheld on jud. review. |
Section 36 Application to DTI/DBERR (Over 50MW) Originally seen as being in ‘Strategic resource area’. Talks ongoing (?) with MOD on radar constraints. Also within the proposed exclusion zone for the Eskdalemuir seismological recording station (see maps). |
||
| Kiln Pit Hill | Nr. Slaley | 6 | 120m. | 2MW | 12MW | NPower | Consented on appeal 12/2/09 |
Inspector rejected Arup and listed buildings protection. See: Appeal Decision (PDF document). |
| Kirkharle | Northside Farm & Bavington Hillhead, nr. Kirkharle | 8(2x4) | 125m. | “up to 3MW” | 18-24MW | NPower | Live Application (18/11/2008). |
NCC Application No. 09/00085/CCMEIA. 2 clusters of 4, c. 1km apart. CREDIT - Campaign for Responsible Energy Development In Tynedale. |
| Kirkheaton | Kirkheaton, nr. Hexham | 3 | 66.5m. | 0.6MW | 1.8MW | EDF/Kirkheaton Wind Farms | Commissioned 2000 |
Nordex turbines.Blades removed on 2 turbines due to faults; inoperative since Autumn 2008.
2002 ROC's/MWh:42,530 2003 ROC's/MWh:3,994; LF:25.3% 2004 ROC's/MWh:4,220; LF:26.8% 2005 ROC's/MWh:3,656; LF:23.2% 2006 ROC's/MWh:4,345; LF:27.6% 2007 ROC's/MWh:4,058; LF:25.7% 2008 ROC's/MWh:1,800; LF:16.7% |
| Lamb Hill | Nr. Edlingham | EHN UK | Mast Rejected. | Mast Application Rejected by then LPA. Not in ‘area of least constraint’. |
||||
| Longhirst | Nr. Longhirst | 6 | 130m. | “up to 2.5MW” | 13MW | Novera | Proposal announced. | Next to RES’s Butterwell/Bluberry scheme. www.noveraenergy.com Contact: Dan Grierson, Project Director - 0131 243 1380. Next to RES scheme. |
| Lynemouth | Lynemouth | 13 | 121.2m. | 2MW | 30MW | CRE/Scottish Power | Consented 01.09 Under construction. |
|
| MSD [Merck, Sharp & Dohme] Pharmaceuticals | Cramlington | 2 | 130m. | 2.5MW | 5MW | Consented (8/08). |
Consented on appeal subject to effects on civil radar (Newcastle Airport) being ameliorated. |
|
| Middlemoor | Nr. N. Charlton | 18 | 125m. | 3MW | 54MW | NPower | Conditional consent (8/8/08) |
Approval conditional on solution to adverse effects on Air Defence Radar at RAF Brizlee Wood being implemented. |
| ‘Moorsyde’ | Shoresdean/Felkington (NT934456) |
7 | 110m. | N/A | N/A | Your Energy (Mistral) |
Refused | Refused by LPA (27/03/08) against planners’ recommendation. Appeal heard (May-June 2009). Appeal rejected 20/01/10 by Secretary of State following Inspector’s recommendation. Moorsyde Action Group. |
| Murton | Murton | 10 | 120m. | 2MW | 20MW | RES (not listed on website) |
Scoping | Moorsyde Action Group (Pro tem). |
| Parkhead/Rayburn Lake | Nr. Netherwitton | 9 | 127m. | 1.8MW | 16.2MW | RES. | Live application (28/8/09). |
|
| Plenmeller | Nr. Haltwhistle | 24 | 92m. | 2MW | 48MW | Harworth Power (UK Coal) | Scoping Mast consented (01/07) |
Northumberland County Council. Not in 'area of least constraint' |
| Ray Estate 1. | Nr. Kirkwhelpington | 16 | 125m. | 3MW | 48MW | Vattenfall | PI held decision awaited |
Joint public inquiry (+ Ray & Steadings) closed 18 Dec. 2008, decision awaited. CREDIT - Campaign for Responsible Energy Development In Tynedale Project originated by AMEC Wind Energy Ltd. who have now sold off their wind interests. Acquired by Swedish company Vattenfall. See website page. |
| Ray Estate 2. | Harwood Forest, Nr. Kirkwhelpington | 22 | 120m. | 3MW | 66MW | Vattenfall | Scoping. | Anem. Mast approved. CREDIT - Campaign for Responsible Energy Development In Tynedale. Project originated by AMEC Wind Energy Ltd. who have now sold off their wind interests. Acquired by Swedish company Vattenfall. See website page. |
| Rimside Moor | Nr. Rothbury | 3 | Rejected (7/03) |
Public Inquiry - rejected on landscape impacts. |
||||
| Steadings (Plashetts) | Nr. Kirkwhelpington | 22 | 120m. | 2-3MW | 44-66MW | Banks Developments | PI held decision awaited |
Joint public inquiry (+ Ray & Steadings) closed 18 Dec. 2008, decision awaited. CREDIT - Campaign for Responsible Energy Development In Tynedale |
| Thockrington | Nr. Bavington | 7 | 100m. | 2MW | 14MW | Wind Prospect | 'shelved' (15/07/06). Scoping revised scheme. |
Anem. Mast consented 2005. Appears that Wind Prospect are reviving this proposal that was “shelved” in July 2006. Previously 14 x 100m. x 2MW. Details of new scheme not confirmed. Local response group: CREDIT - Campaign for Responsible Energy Development In Tynedale. |
| Todburn East | Longhorsley, 2km. | 8 | 125m | 3MW | 24MW | Coronation Power | Proposal announced. | Anem. Mast appr. 7/06. |
| Todd Hill | Between Pigden and Stanton. |
4 | 101m. | 2-2.5MW | “8-10MW” | Novera | Live application (04/12/2008) | NCC Planning Ref. No. 09/00083/CCMEIA. Novera contact: Dan Grierson, Project Director - 0131 243 1380. |
| Toft Hill | Nr. Grindon/Shellacres (NT906436) |
7 | 112m. | 2.7MW | 19MW | NPower | Refused | Refused by LPA (27/03/08) following planners’ recommendation. Appeal heard (May-June 2009). Appeal rejected 20/01/10 by Secretary of State following Inspector’s recommendation. |
| Tone Hall | W. of A68 Nr. Sweethope Lough | 6 | ? | 2MW | 12MW | Nuon Renewables | Scoping (02/02/2007) | Local response group: CREDIT - Campaign for Responsible Energy Development In Tynedale. |
| Wandylaw | Nr. N. Charlton | 10 | 125m. | 2-3MW | 20-30MW | Ridgewind | Consented | Consented on appeal 10/2/09. See: Appeal Decision (PDF document). |
| Wansbeck Hospital | Ashington | 1 | 43m. | 0.1MW | 0.1MW | Inoperative | Vestas V20-100 turbine. Shut down since 2007 due to blade damage (delamination). Health trust have commissioned external report on repair/replacement. 1992 MWh:22.8; LF:N/A 1993 MWh:115.8; LF:13.2% 1994 MWh:162.3; LF:18.5% 1995 MWh:152.4; LF:17.3% 1996 MWh:151.3; LF:17.2% 1997 MWh:133.5; LF:15.2% 1998 MWh:122.6; LF:13.9% 1999 MWh:105.6; LF:12.0% 2000 MWh:129.3; LF:14.7% 2001 MWh:119.2; LF:13.6% 2002 MWh:128.1; LF:14.6% 2003 MWh:112.7; LF:12.8% 2004 MWh:79.8; LF:9.1% 2005 MWh:130.9; LF:14.9% 2006 MWh:126.1; LF:14.3% 2007 MWh:27.1; N/A 2008 MWh:0.0 2009 MWh:0.0 |
|
| West Ancroft | North Ancroft | 8 | 115m | 2.25MW | “approx. 18MW” | E.On UK. | Live Application (09/04/09). |
NCC Planning Ref. No. 09/00063/CCMEIA. Contiguous with 'Moorsyde' site. West Ancroft Community Action (WACA). See also: MAG website. |
| West Moneylaws | Nr. Mindrum, Cornhill. | 6 | 125m. | 3 | 18MW | Coronation Power | Abandoned | Abandoned after scoping (01/07) Grid connection Proximity Nat. Pk. |
| Whinney Hill | Nr. Netherwitton | ? | 1??m. | ?W | ??MW | Force9 Energy | Scoping | Mast consented 07/03. |
| Wingates | Wingates | 6 | 110m | 2 to 2.5MW | 12 to 15MW | Novera Energy | Live application (Dec. 2008). | NCC. (A/2008/0604). Consent for 70m mast (with lights) 26/2/09. Local response group: Wingates NOT Wind Farms (WNWF). |
| Wingates Moor | Nr. Wingates | 4 | 100m | 2.00-2.5MW | 8 to 10MW | BT | Scoping. | NCC. Split site, another 6 turbines proposed for East Wingates Local response group: Wingates NOT Wind Farms (WNWF). |
| East Wingates | Nr. Wingates | 6 | 100m | 2.00-2.5MW | 12 to 15MW | BT | Scoping. | NCC. Split site, another 4 turbines proposed for Wingates Moor Local response group: Wingates NOT Wind Farms (WNWF). |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Eco Centre, Hebburn | Hebburn | 1 | 45.5m. | 0.225MW | 0.225MW | Groundwork, South Tyneside | Operating (8/05) | Single, small embedded turbine
First appears on register March 2007. 2006 ROC's/MWh:86 2007 ROC's/MWh:236; LF: 11.9% 2008 ROC's/MWh:233; LF: 11.8% |
| Nissan | Sunderland | 8 | 51m. | 0.66MW | MW | Nissan | Operating (11/05) | Small embedded turbines
SH Vestas V47. 2 more turbines consented in 2007. Turbine fire December, 2005. 2005 ROC's/MWh:0 2006 ROC's/MWh:4,534 2007 ROC's/MWh:7,175; LF: 20.7% 2008 ROC's/MWh:8,559; |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| ‘A1’ | “between Newton Aycliffe and Bradbury” | 10 | 121m. | 2-2.5MW | 20-25MW | E.ON UK | Live Application | |
| Barningham High Moor | Nr. Barningham | 25 | 54m. | 15MW | National Wind Power | Refused | Refused locally and at appeal 1998. National Wind Power (NWP) failed in its attempt to persuade the High Court to overturn The Secretary of State's
decision to refuse the grant of planning permission, 1999.
|
|
| Broom Hill | Nr. Tow Law (NZ 159392) |
4 | 102m. | 2MW | 8MW | EDF | Operating (06/02/2009) |
Ref. No. 3/2006/0087. Four REpower MM82 turbines. Causing TV problems for local residents, see Press. |
| Butterwick Moor | Nr. Sedgefield | 10 | 110m. | 2-2.5MW | 20-25MW | E.ON.UK | Consented (18/06/2007) | Immediately adjacent to Walkway scheme. REpower has won the turbine contract (announced Dec. 2009). |
| ‘Crake Scar’ | Nr. Woodland | 4 | 115m. | 2MW | 8MW | Arcus for Bolsterstone Innovative Energy (Woodland) Ltd. |
Scoping | |
| Edder Acres | Nr. Shotton Colliery | 2 | 11.2m. | 2.3MW | 4.6MW | A7 Energy | Refused 15/11/07 |
Re-submission refused
Refused 2005 Appeal refused. |
| Fox Cover | Nr. Dawdon and Cold Hesledon, Seaham | 2 | 125m. | 3MW | 6MW | EDF Energy | Refused 01/07/08 |
Just to N. of A182. Refused by Easington DC, then LPA. |
| Foxton Lane/Shotton Beck | Heley House Farm, nr. Sedgefield | 3 | 1??m. | 2MW | 6MW | Wind Prospect | Scoping | Anem. mast approved (7/09)- Appl. No. 7/2009/0239/DM. DCC Case Officer: David Walker. |
| Great Eppleton | Nr. Hetton-le-Hole (NZ 366 485) |
4 | 69.5m. | 0.75MW | 3MW | Powergen/E.ON.UK | Shut down 2005. Repowering application 12/1/07 (see below). | 4 x 69.5m 2-blade turbines (operating 1997-2004).
2002 ROC's/MWh:2,934 2003 ROC's/MWh:2,932; LF:11.2% 2004 ROC's/MWh:3,941; LF:15.0% 2005 ROC's/MWh:0; LF:0% |
| Great Eppleton | Nr. Hetton-le-Hole (NZ 366 485) |
4 | 115m. | 2MW | 8MW | E.ON.UK | Consented | Repowering scheme.
REpower MM92 turbines. |
| The Greenhouse (Greencroft) | Nr. Consett | 1 | 43.5m. | 0.225MW | 0.225MW | Groundwork w. Durham | Operating 2006 | Small embedded.
2006 ROC's/MWh:216; 2007 ROC's/MWh:286; [LF:14.5%] 2008 ROC's/MWh:203; [LF:10.2%] [Ofgem changed TIGC from 225 to 97kW in mid 2006 after 5 months of operation. Reason is not clear. This then gives ludicrously high LF figures - our calculated figures are in brackets]. |
| GSK | Barnard Castle | 2 | 45m. | 0.25MW | 0.5MW | Glaxo Smith Kline | Operating | Small embedded scheme
SH Micon turbines. 2004 ROC's/MWh:261; LF:N/A 2005 ROC's/MWh:389; LF:8.9% 2006 ROC's/MWh:359; LF:8.2% 2007 ROC's/MWh:441; LF:10.1% 2008 ROC's/MWh:414; LF: 9.5% |
| Hare Hill | Nr. Peterlee (NZ 371 414) |
2 | 100m. | 2.75MW | 5.4MW | Powergen/E.ON.UK | Operating (2004) | NEG Micon NM80 turbines.
Hare Hill WTG 1 (2.314MW Cap.): 2004 ROC's/MWh:1,795; LF:N/A 2005 ROC's/MWh:3,732; LF:18.4% 2006 ROC's/MWh:4,305; LF:21.2% 2007 ROC's/MWh:4,305; LF:21.2% 2008 ROC's/MWh:5,649; LF:27.9% Hare Hill WTG 2 (2.75MW Cap.): 2004 ROC's/MWh:1,625 2005 ROC's/MWh:3,510; LF:14.6% 2006 ROC's/MWh:3,898; LF:16.2% 2007 ROC's/MWh:5,279; LF:21.9% 2008 ROC's/MWh:4,104; LF:17.0% |
| Haswell Moor | Nr. Haswell/Sherburn | 5 | 110m. | 2.3MW | 11.5MW | E.ON.UK | Consented (01/08) | REpower has won the turbine contract (announced Dec. 2009). |
| Hawthorn | West of A19, nr. Murton (NZ405460/NZ408463). | 2 | 105m. | 2.5MW | 5MW | SLP Energy | Live application | Initial application April 2008, withdrawn September 2008. Resubmitted (Non-technical summary available). |
| High Haswell | Nr. Haswell | 2 | 100m. | 2-2.5MW | 4-5MW | Hallam Land Management | Consented (01/08) | |
| High Hedley Hope | Nr. Tow Law | 3 | 71m. | 0.75MW | 2.25MW | EDF/London Power Co. | Operating (2002) |
2002 ROC's/MWh:3,493
2003 ROC's/MWh:5,394; LF:27.4% 2004 ROC's/MWh:6,352; LF:32.2% 2005 ROC's/MWh:6,665; LF:33.8% 2006 ROC's/MWh:5,638; LF:28.6% 2007 ROC's/MWh:6,285; LF:31.9% 2008 ROC's/MWh:5,470; LF:27.8% |
| High Hedley Hope 2 | Nr. Tow Law | 4 | 105m. | 1.3MW | 5.2MW | EDF/London Power Co. | Operating (10/08) |
Nordex N60 turbines. 2008 ROC's/MWh:5,616; |
| High Sharpley | Nr. Seaham. | 2 | 90m. | 1.3MW | 2.6MW | Cornwall Light & Power Company Ltd./REG | Operating (2007) | See also refused extension at South Sharpley.
Nordex N60 turbines 2007 ROC's/MWh:5,379 2008 ROC's/MWh:6,476; LF:28.4% |
| High Volts | Elwick, Hartlepool (NZ 450 335) |
3 | 100m. | 2.75MW | 8.1MW | Powergen | Operating (2004) | NEG Micon NM80 turbines.
High Volts 1 (2.314MW Cap.): 2004 ROC's/MWh:6,124; LF:30.1% 2005 ROC's/MWh:4,090; LF:20.1% 2006 ROC's/MWh:1,340; LF:6.6% 2007 ROC's/MWh:5,411; LF:26.6% 2008 ROC's/MWh:5,000; LF:24.6% High Volts 2 (5.54MW Cap.): 2004 ROC's/MWh:6,970; 2005 ROC's/MWh:8,875; LF:18.4% 2006 ROC's/MWh:7,450; LF:15.5% 2007 ROC's/MWh:10,302; LF:21.4% 2008 ROC's/MWh:9,013; LF:18.7% |
| Holmside | Nr. Stanley (NZ 208 503) |
2 | 100m. | 2.75MW | 5.5MW | Powergen | Operating (2004) | NEG Micon NM80 turbines.
Holmside WTG 1 (2.314MW Capacity): 2004 ROC's/MWh:2,584 2005 ROC's/MWh:4,040; LF:19.8% 2006 ROC's/MWh:3,300; LF:16.2% 2007 ROC's/MWh:5,306 2008 ROC's/MWh:4,663; LF:23.0% Holmside WTG 2 (2.75MW Capacity): 2004 ROC's/MWh:2,184 2005 ROC's/MWh:4,596; LF:19.1% 2006 ROC's/MWh:3,431; LF:14.2% 2007 ROC's/MWh:4,042; LF:16.8% 2008 ROC's/MWh:3,219; LF:13.4% |
| INEOS Newton Aycliffe Ltd. (Formerly Hydro Polymers). |
Newton Aycliffe | 2 | 48m. | 0.25MW | 0.5MW | Hydro Polymers/TNEI | “Project cancelled” (2008). | Small embedded scheme Plastics plant. |
| Langley | Nr. Burnhope (NZ200 474) |
4 | 102m. | 2MW | 8MW | EDF | Operating | REpower MM82 turbines. Consented 6/05. Commissioned 13/08/2008. 2008 ROC's/MWh:4,921 |
| Oakenshaw | Nr. Oakenshaw | 3 | 1??m. | 2.75MW | 8.25MW | EDF Energy | Pre-planning | |
| Quarrington Hill | Nr. Cassop | 2 | 3MW | 6MW | Eco energy | Refused (2004) | Appeal rejected |
|
| Sheraton Hill | Nr. Wingates | 3 | 3MW | 9MW | ? | Unclear | Originated by United Utilities Not listed by E.ON.UK who acquired UU's wind portfolio in 02/05. |
|
| South Sharpley | Nr. Seaham, Co Durham | 3 | 100m. | 2.5MW | 7.5MW | Cornwall Light & Power Company Ltd./REG | Refused (22/12/2009) |
Extension to existing scheme at High Sharpley. Unanimous refusal following officer’s recommendation. Major reason: proximity to housing (450m). |
| Stanley Moss | Nr. | 2 | 107m. | 2.3MW | 4.6MW | Amec/Banks Group | Refused (6/04) |
|
| Stobhill | Nr. Bolam | 7 | Up to 125m. | 2-2.5 MW | 14-17.5MW | NPower | Announced | |
| Tow Law | Nr. Tow Law | 3 | 71m. | 0.77MW | 2.31MW | National Wind Power | Operating | Nordex N50 turbines, commissioned 01/12/2001.
2002 ROC's/MWh:3,417 2003 ROC's/MWh:5,295; LF:26.2% 2004 ROC's/MWh:6,424; LF:31.7% 2005 ROC's/MWh:6,231; LF:30.8% 2006 ROC's/MWh:5,677; LF:28.1% 2007 ROC's/MWh:4,378; LF:21.6% 2008 ROC's/MWh:4,180; LF:20.7% |
| Trimdon Grange | Nr. Trimdon | 4 | 76m. | 1.3MW | 5.2MW | EDF | Operating (10/07/2008) |
Nordex N60 turbines. Consented on appeal, 2005. 2008 ROC's/MWh:3,754 |
| Walkway | High Swainston Nr. Sedgefield |
7 | 110m. | 2 | 14MW | Wind Prospect | Operating (04/2008) |
REpower MM82 turbines.
Immediately adjacent to Butterwick scheme. Operating as 2 entitities (Walkway 1 [R.O. ID R00197RQEN], 4 turbines & Walkway 2 [R.O. ID R00198RQEN], 3 turbines) Walkway 1 2008 ROC's/MWh:7,200 Walkway 2 2008 ROC's/MWh:9,201 |
| ‘West Durham’ | Nr. Satley/Tow Law | 12 | 100m. | 2MW | 24MW | Banks Developments |
Operating (5/09) |
REpower MM82 turbines. |
| ‘Windy Bank’ | Nr. Woodland | 5-9 | 115m. | 2-3MW | 10-27MW | Banks Developments | Scoping | Contiguous with Crake Scar (see above).
|
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Red Gap Farm | Wolviston, Hartlepool | 5 | 125m. | 3MW | 15MW | BT | Approved (3/2/2010). |
Ref. H/2009/0231. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Middlesbrough Football Club | Middlesbrough | 1 | 90m | 3MW | 3MW | Middlesbrough FC | Approved |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Teesside Offshore | 1.5km off Coatham Sands, Redcar | 30 | ?140m. | 2.5MW | 75MW | Northern Offshore Wind/EDF | Consented 17.09.2007 | Section 36 decision by BERR (DTI) Redcar & Cleveland Co. may seek judicial review. |
| Teeswind North | Corus steel site, Redcar | 18 | 140m. | 2.5MW | 45MW | AMEC Wind/Corus | Consented (16.07.02 - R/2001/936/FF) "In abeyance" |
|
| Tees Wind South | Corus steel site, Redcar (NZ 545 220) |
10 | 140m. | 2.5MW | 25MW | AMEC/Corus | "In abeyance" |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Augean Landfill Site | Port Clarence, Nr. Billingham. | 4 | 126m. | ? | ? | Augean PLC | Scoping | |
| Seamer | Between Hilton and Seamer, nr. Yarm, on Stockton-on-Tees and N. Yorks boundary. | 5 | 125m. | “Up to 3MW” | “Up to 15MW” | Broadview Energy | 3 consented, 2 refused. | Refused against recomm. by Stockton Borough Council (11/08) and Hambleton District Council [Yorkshire] (10/08). Revised appl. approved on Chair's vote by SBC (3 turbines); HDC has refused the other 2 on 17/9/09 (7:5). Article 14 hold on approval by the Government Office North East, the Secretary of State has now rejected a call-in (see press report,29 August 2009) . SHWAG - Seamer & Hilton Windfarm Action Group |
| Stillington/Lamb's Hill | Stillington, nr, Stockton | 4-6 | 1??m. | ?MW | ?MW | Banks Developments/Gaz de France | Scoping | Project would include a small combined heat and power (CHP) plant on Stillington Industrial Estate. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| East/West Newbiggin | Nr. Sadberge, Darlington. | 9 & 2 | 100m. | ?MW | ?MW | Pure Renewable Energy, PB Power. | project announced | 2 adj. sites with 9 & 2 tubines. Darlington Borough Council. |
| Moor House | Nr. Barmpton, Darlington. | 10 | 100 & 110m. | 2-2.5MW | 20-25MW | Banks Developments | Application | Banks Contact: Emily Hooson - 01740 658500 or e-mail: moorhouse@banksdevelopments.com Application Reference: 09/00741/FUL. |
| Royal Oak | Nr. Shildon | 5 | 105m. | 1.3MW | 6.5MW | EDF/Harworth Power (UK Coal). | Consented (10/05) |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Harrows Law | Nr. Tarbrax | 37 | 110m. | 3MW | 111MW | Scottish and Southern Energy | Pre-planning | Section 36 proposal (over 50MW)in Pentland Hills on the West Lothian/South Lanarkshire border. First submitted June 2005. “We are currently in the process of re-designing this proposal and hope to submit an application later this year.” (Website, June 2009.) |
| Pates Hill | Nr. West Calder | 7 | 107m. | 2MW | 14MW | Your Energy | Under construction. | Consented June 2007. project bought from ‘New Lives New Landscapes’. Adjacent to PM Renewables’ consented 15-turbine Tormywheel project, developed with Mistral/Your Energy, as at Drone Hill, Coldingham. Vestas V-80 turbines. |
| Tormeywheel | Fauldhouse | 15 | 102m. | 2.75MW | 41.25MW | PI Renewables (with Mistral) |
Under construction. | Consented June 2007. See appeal decision. Near to other schemes at Black Hill (Lanarkshire) and Pates Hill (W Lothian). |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Auchencorth Moss | Nr. Penicuik (NT210567) |
14 | 102m. | 2.5MW | 35MW | E.On UK | Appealed PI in progress. |
Midlothian Council Refused 11:3 following Officer's rec. Appealed 27/08/08 - DPEA Appeal Ref. P/PPA/290/169. Response Group: PEPA |
| Bowbeat extension | Nr. Peebles | 1 (5) | 110m | 2.3MW | 9.2MW | E.ON UK | Scoping (2008) | 4 turbines in Midlothian, 1 in Scottish Borders.
|
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Aikengall | Nr. Innerwick (NT694694) |
16 | 125m. | 3MW | 48MW | Community Windpower Ltd. | Operational (5/09). |
Vestas V90 turbines. Consented 13/03/07, against Officer's advice by Convenor’s casting vote. Site in AGLV, SSSI within site. Contiguous with Crystal Rig. Unlike CR, is very visible from the coast. |
| Aikengall II (‘Wester Dod’) | Monynut Edge, Nr. Innerwick (NT512676) |
23 (30) | “up to 145m” | “up to 3.6MW” | 82.8MW (108MW) | Community Windpower Ltd. | Live Application | 23 in East Lothian, 7 in SBC area. Section 36 application to Scottish Executive. Twice the size of the original application! Response group: Save the Lammermuirs (STL). |
| Crystal Rig 2. | (NT660690) | 52 | 30x110m 22x125m. |
128.8MW | Natural Power | Under construction. | Consented (01/05/04), 23 Turbines in Sc. Borders 29 in East Lothian. Site in AGLV. |
|
| Crystal Rig 'Phase IIa' | (NT678678) | 9 | 125m. | 3MW | 27MW | Natural Power | Under construction. | Nos. Increase to Crystal Rig 2. Site in AGLV. |
| Dunbar Cement Works | Nr. Dunbar | 3 | 125m. | 3MW | 9MW | EDF | Scoping | In 2008, Lafarge announced its intention to install three 125m wind turbines at its Dunbar Works.
Four exhibitions were held on the company’s proposals, developed in conjunction with EDF Energy Renewables. See PR statement. Response group: Save the Lammermuirs (STL). |
| Keith Hill | NE of Dun Law (Soutra) adj. to Pogbie | 10 | 93.5m. | 2-2.5MW | 20-25MW | Ron Shanks Development for G & M Hodge and Son. | Live Application | |
| Pogbie | Pogbie, Nr. Soutra Law | 6 | 76m. | 850kw (Vestas V52) | 5.1MW | Pogbie Farms, Agent: Natural Power | Consented (02/09/09) |
Planning Ref. 08/00823/FUL. East side of A68, Just north of Dun Law I/II. |
| Spott Roundabout | A1, Layby E. Of Spott Roundabout, nr. Dunbar | 1 | 32m. | N/A | N/A | Community Wind Power | "Application withdrawn" | Application withdrawn, 03/03/10. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Aikengall II (‘Wester Dod’) | Monynut Edge, Nr. Innerwick (NT512676) |
7 (30) | 145m. | “up to 3.6MW” | 25.2MW (108MW) | Community windpower | Live application | 7 of 30 turbines in SBC area. Section 36 application to the Scottish Executive. SBC Scoping opinion sought. Response group: Save the Lammermuirs (STL). |
| Alemill Farm | Nr. Eyemouth | 8 | ?m. | ?MW | ?MW | ? | Scoping | SBC Scoping opinion sought 06.06.07 |
| Blackburn | Blackburn Farm, nr. Grantshouse (NGR 7866) |
14 | 125m. | ?MW | ?MW | Volkswind | Scoping | |
| Black Hill | Nr. Duns (NT735600) |
22 | 78m. | 1.3MW | 28.6MW | RES | Operating (01/07) | Siemens turbines.
2006 ROC's/MWh:2,437 2007 ROC's/MWh:78,881 2008 ROC's/MWh:81,252; LF:32.4% |
| Blaewearie | Nr. Clovenfords (341 639) |
“Up to 6 turbines” | 1??m. | ?MW | ?MW | Lomond Energy | Pre-scoping | Scoping opinion requested from SBC, 07/10/10.. |
| Border Precision | Pinnacle Hill Ind. Est., Kelso | 1 | 70m. | 0.85MW | 0.85MW | Wind Direct | Consented (02/08) | Refusal recommended by PO on grounds of visual impact.
|
| Emly Bank (Bowbeat) | Peebles (NT285475) |
12 | 76m. | 1.3MW | 15.6MW | E.ON UK | Operating (2001) | Appl. 00/00371/FUL, appr. 25/09/2000
Nordex N60 turbines. 2002 ROC's/MWh:11,061 2003 ROC's/MWh:32,602; LF:24.8% 2004 ROC's/MWh:35,862; LF:27.3% 2005 ROC's/MWh:36,474; LF:27.8% 2006 ROC's/MWh:34,600; LF:26.3% 2007 ROC's/MWh:35,197; LF:26.8% 2008 ROC's/MWh:37,085; LF:28.2% |
| Roughside Hill(Bowbeat) | nr. Peebles (NT285475) |
12 | 76m. | 1.3MW | 15.6MW | E.ON UK | Operating | Appl. 00/00371/FUL, appr. 25/09/2000
Nordex N60 turbines. 2002 ROC's/MWh:10,361 2003 ROC's/MWh:33,539; LF:25.5% 2004 ROC's/MWh:35,987; LF:27.4% 2005 ROC's/MWh:37,736; LF:28.7% 2006 ROC's/MWh:35,860; LF:27.3% 2007 ROC's/MWh:39,354; LF:29.9% 2008 ROC's/MWh:38,633; LF:29.4% |
| Bowbeat Extension | Nr. Eddleston (NT288473) | 1 (5) | 110m. | 2.3MW | 2.3MW (12.5MW) | E.ON UK | Scoping | 1 turbine in SB. 4 in Midlothian.
Scoping opinion provided 01.08.08 |
| Broadmeadows | Yarrowford, nr. Selkirk (NT410315) |
13 | 112m. | “between 2 and 3MW” | 36MW | Green Power | Live Application (23.12.04) |
Appl. No. 04/02501/FUL Broadmeadows Action Group |
| Brockholes | Brockholes Farm, nr. Grantshouse (NT815663) |
3 | 84m. | 0.9MW | 2.7MW | Green Cat Renewables for Mr J Prentice |
Live Application (10.04.09) |
|
| Brotherstone | Nr. Dun Law | ?29 | 1??m. | ?MW | ?MW | Ridgewind | Pre-scoping | Pre-scoping meeting with SBC held (11/11/09). |
| Brunta Hill | Nr. Westruther (NT597514) |
11 | 125m. | 3MW | 33MW | Atmos Consulting | Scoping | Scoping opinion requested from SBC 05/11/09, provided 21/12/09. Response group: Save the Lammermuirs (STL). |
| Carcant | Nr. Heriot (NT362528) |
3 | 107m. | 3MW | 9MW | Airtricity | Under construction. | SBC Appl. No. 05/01884/FUL. Airtricity, acquired from AMEC. Consented (09.06) |
| Corbie Shank, Craik Forest | Craik Forest, nr. Hawick (NT337007) |
73 | N/A | ca. 150MW | REC Ltd. | Scoping | SBC. Sect 36 scoping opinion provided 08.04.03 |
|
| Crystal Rig - 'Phase 1'. | (NT678678) | 20 | 100m. | 2.5MW | 50MW | Fred Olsen Renewables/ Natural Power |
Operating (2003) | Appl 01/00269/FUL, appr. 10.09.01
Site in AGLV. Extension & C.R. Phase 2 consented, see below. 2003 ROC's/MWh:2,941 2004 ROC's/MWh:75,312; LF:17.2% 2005 ROC's/MWh:120,234; LF:27.5% 2006 ROC's/MWh:110,414; LF:25.2% 2007 ROC's/MWh:111,576; LF:25.5% 2008 ROC's/MWh:104,257; LF:23.8% |
| Crystal Rig - ‘Phase 1a’. | (NT660690) | 5 | 125m. | 2.5MW | 12.5MW | Fred Olsen Renewables/ Natural Power |
operational | Site in AGLV. |
| Crystal Rig - ‘Phase 2’. | (NT678678) | 23 (52) | 30x110m 22x125m. |
128.8MW | Fred Olsen Renewables/ Natural Power |
Under construction | Section 36 appl. 01.05.04, 23 Turbines in Sc. Borders 29 in East Lothian. Consented (01.05.04).Site in AGLV. |
|
| Crystal Rig - 'Phase 2a' | (NT678678) | 9 | 125m. | 3MW | 27MW | Fred Olsen Renewables/ Natural Power |
Under construction | Nos. Increase to Crystal Rig 2. Site in AGLV. |
| Drone Hill/Coldingham Moor | Nr. Coldingham (NT853685) | 22 | 76m. | 1.3MW | 28.6MW | PM Renewables: jt. venture by PI Renewables/ Mistral Invest |
Consented (11/08) | SBC Appl. No. 05/00425/FUL. Unanimous vote to follow officer's recommendation to refuse. Consented on appeal, November 2008: Appeal Decision Notice. |
| Dunion Hill | Nr. Denholm & Jedburgh (NT615157) |
8 | 101m. | 2.3MW | 18.4MW | Windjen Power | Refused at appeal. | Appl. No. 05/02336/FUL, 13.01.06. Refused SBC 10.09.07. Refused on appeal 9.04.09 (first refusal on appeal for SBC). See Decision document. Dunion Hill Conservation Group |
| Dun Law [Soutra] . |
Nr. Soutra (NT460560) |
26 | 67.5m. | 0.66MW | 17.16MW | RES for Sc. Power |
Operational (2000) | RES for Scottish Power Renewables (owned by Iberdrola Renewables). Appl. No. 96/01130/FUL. Appr. 31.07.97 Vestas V47 0.66MW turbines. 2002 ROC's/MWh:23,112 2003 ROC's/MWh:36,292; LF:24.1% 2004 ROC's/MWh:45,421; LF:30.2% 2005 ROC's/MWh:42,122; LF:28.0% 2006 ROC's/MWh:38,192; LF:25.4% 2007 ROC's/MWh:37,022; LF:24.6% |
| Dun Law 2. (Soutra) |
Nr. Soutra (NT465575) |
35 | 75m. | 0.85MW | 29.75MW | RES for Sc. Power |
Operational | Appl. No.05/00847, consented 09/07. Vestas V52 turbines. Scottish Power Renewables (owned by Iberdrola Renewables). |
| Earlshaugh | Nr. Moffat (NT080155) |
36 | 125m. | “Up to” 3MW | “Up to” 108MW | Wind Energy Ltd | Live Application PI now due. |
Section 36 Application July 2008. SBC objected (Nov. 2008). Local response group: (SOS) Save Our Scenery |
| East Gordon | Nr. Gordon | ? | ?m | ? | ? | ? | Pre-scoping. | SBC. |
| Fala Hill | Nr. Heriot (NT338655) |
3 | 101m. | 2.3MW | 6.9MW | E.ON.UK | Refused | Appl. No. 04/02420/FUL. Refused SBC 8/5/06. |
| Fallago Rig/Ridge Mk. II | Nr. Longformacus (NT570600) |
48 | 100 & 125m. | 3MW | 144MW | North British Windpower | Live application PI held. PI to re-open. |
Section 36 Application 16.05.05 (Mk. I). Mk. II - numbers reduced from 62 (01/07). SBC objection 05.02/07 PI held. PI to re-open to rubber stamp approval after hearing new MOD radar evidence. We now hear that the PI, under threat of legal action will hear all new evidence, not just radar (see Berwickshire News, 18 November 2009). Response group: Save the Lammermuirs (STL). |
| Frogden Farm | Nr. Kelso | 9 | 100m. | 1.5MW | 13.5MW | Wind Hydrogen Ltd. | Scoping. | SBC. “Scoping opinion sought 22.8.07” |
| Glenkerie (Kingledores) | Nr. Tweedsmuir (NT092279). |
11 | 6 x 105m. 5 x 120m. |
1.8-2.5MW | 19.8-27.5MW | Novera | Consented | SBC appl. no. 07/02478/FUL. Consented SBC (08.09.08). Cleared for approval by SE 27.10.08. |
| Greenvale | Craigswalls, Chirnside (NGR 845 558) |
1 | c. 100m | ? | ? | Greenvale | Pre-scoping. | SBC. “Pre-scoping/pre-application submissions received 08.09.09”. |
| Halkburn (Long Park) | Nr. Stow (NT480420) |
19 | 110m. | 2MW | 38MW | Wind Prospect | Operational | Appl. No. 04/00317/FUL. Refused SBC (31/8/05)- landscape impacts. Consented on appeal: Appeal Decision Notice. REpower MM82 turbines. |
| Hawick | Nr. Pilmuir, Hawick | ? | ?m. | ? | ?MW | ? | Pre-scoping | On Common Good Land near Williestruther Loch. Proposed by ‘A Greener Hawick’ (see ‘Ill wind blows over turbine site proposal’, Hawick News, 11/02/2010). |
| Heathpool | Nr. Eddleston (NT255455) |
6-7 | ? | ? | Ridge Wind | Pre-scoping. | SBC. “Pre-scoping opinion discussions, no scoping opinion requested”. |
|
| Hoprigshiels | Nr. Oldhamstocks | 5 | 125m | ? | Pre-scoping. | SBC. |
||
| Kinegar Quarry | Nr. Cockburnspath (NT376376 669840) |
2 | 130m. | 2.5MW | 4MW) | Kinegar quarry (S R Findlay). Wind Direct |
Pre-application. | SBC scoping opinion 13.07.09, anem. mast approved 06.05.09. Nordex N100 turbines. Response group: Save the Lammermuirs (STL). |
| Langhope Rig | Nr. Ashkirk (NT406203). |
10 | 100m. | 2.3MW | 23MW | Airtricity | Consented. | SBC Appl. No. 06/01236FUL. Appl. Refused 07.07. Consented on appeal 05.08: Appeal Decision Notice. |
| Hyndhope/W Alemoor (Langhope Rig Extension) |
Nr. Hyndhope. | 10-15 | 125m. | ?MW | ?MW | Natural Power Consultants | Scoping. | SBC scoping opinion provided 24.02.09. |
| Leithope | Nr. Carter Bar (NT715095) |
32 | 115m. | 70MW | Npower | Scoping | SBC Sect 36 scoping opinion provided 22.12.05 |
|
| Middle Hill | Nr. Tweedsmuir | 11 | 105m | 2.45MW | 27MW | West Coast Energy | Scoping. | SBC. Scoping opinion provided 12/09/05. |
| Minch Moor | Nr. Innerleithen | 12 | 100m. | 2MW | 24MW | Vattenfall | Live application | Local response group: Stop Minch Moor Windfarm. Project originated by AMEC, sold to Swedish company Vattenfall. See website page. |
| Monashee | Nr. Grantshouse (NT801611) | 17 | 70m. | 15MW | West Coast Windfarms | Unclear | SBC Scoping opinion 9/03. Response group: Save the Lammermuirs (STL). |
|
| North Common, Selkirk | Selkirk | 6 | 125m. | ?MW | ?MW | Selkirk Regeneration Group | Scoping | SBC scoping opinion provided 24/06/09. Map and other docs on Selkirk Community Council website. |
| Penmanshiel Moor | Nr. Grantshouse (NT822678) |
19 | 125m. | 2.5MW | 47.5W | RES | Scoping | Scoping opinion sought from SBC 04/12/09. |
| Rowantree | Nr. Fountainhall (NT467500) |
23 | 125m. | 3MW | 69MW | RWE NPower | Live application (02/2010) |
Section 57 application (over 50MW). Non-technical summary available free of charge from RWE NPower (Tel. 01738 825110) Scoping document downloadable here. Representions to Energy Consents at the Scottish Government or by email to energyconsents@scotland.gsi.gov.uk by not later than Monday 22 March 2010. |
| Sell Moor | Nr. Oxton (NT480444) |
19 | 115m. | 2.5MW | 47.5MW | RDC | Refused | Appl. No. 04/00350/FUL. Refused SBC (31/8/05). Toddleburn Action Group. |
| Spurlens Rig | Nr. Leadburn (NT248538). |
5 | 125m. | 2MW | 12.5MW | Lomond Energy | Scoping | SBC scoping opinion provided 21/04/08 and 16/08/08. APEAL - Association to Protect the Environment at Leadburn. |
| Standhill | Nr. Denholm (NT563233) |
3 | ?m | ? | ? | Greenspan Agency | Scoping. | SBC. Scoping opinion requested 08/09/09 |
| Sunwick | Nr. Hutton | 5 | 145m | 2MW | 10MW | RD Energy Solutions | Pre-scoping. | SBC. “Screening request received 18 June 2009. Opinion provided 17 July 2009.” |
| Toddleburn | Nr. Oxton (NT450531) |
12 | 110m. & 125m. | 3MW | 36MW | Scottish & Southern Energy | Operational. | Appl. No.04/01744/FUL. Refused SBC (31/8/05)- landscape impacts. Consented (Jan. 07) on appeal: Appeal Decision Notice. |
| Upper Kidston Farm | Nr. Peebles (NT224424) |
Max. 10 | ? | ? | Volkswind | Pre-scoping. | SBC. “Pre-scoping opinion discussions, no scoping opinion requested”. |
|
| Whitton | Nr. Morebattle (NT748207). |
6 | 110m. | “up to 3MW” | up to 18MW | Vattenfall | Live application. | SBC Appl. No. 09/01162/FUL. You can comment online on the application. Local response group: Protect Your Cheviots. Project originated by AMEC, sold to Swedish company Vattenfall. See website page. |
Every effort has been taken to ensure that the information published on this web site is accurate. However, windbyte.co.uk can accept no liability for the accuracy of content which has been gathered from other published sources. Visitors who rely on this information do so entirely at their own risk.
If you find any errors - please email corrections to the webmaster.