Windbyte Name Banner

QUICK NAVIGATION:


INTRODUCTION


‘SECTION 36’ APPLICATIONS

Schemes of over 50MW capacity - even if they would only produce a fraction of this amount in operation - are submitted to for determination by a Minister according to Section 36 of the Electricity Act 1989 (or the equivalent Section 57 of the Town and Country Planning (Scotland) Act 1997). This was originally intended as a mechanism for major projects that were considered to be in the national interest. It is questionable whether it was intended as a mechanism for developers to sideline the local planning process with wind power projects having a theoretical maximum capacity of just over 50MW, and which would produce as little as 20% to 30% of that headline capacity in operation.

Some developers regard Section 36 applications as standing more chance - they are, after all, being decided by a Minister who is also responsible for implementing current energy policy - than would smaller schemes with local planners who are more inclined to reflect the concerns of their local communities and the local economy. A public inquiry can be triggered by the formal objection of a local planning authority, but the developers know very well that cash-strapped local authorities and poorly funded community groups are then forced to find large sums of money in order to secure legal representation. At the end of the day, the Secretary of State can, but seldom does, override an inspector's recommendation.

POWER OUTPUT

Peak theoretical capacity figures are given for turbines and sites. The intermittent nature of wind power means that the capacity or load factor of wind turbines can be anything between 8% and 40% of the headline figure, depending on the wind resource on site. The BWEA likes to claim that onshore wind turbine arrays usually have a capacity factor of 30%; our regional planners assume a figure of 29/30%. The March 2006 issue of 'Energy Trends', produced by the Department of Trade and Industry, has a table of capacity, or load, factors for onshore wind farms in the UK produced from actual production figures. This table shows that the North East has the lowest recorded load factor in the country: for 2003 the figure was 19%; for 2004 the figure was 21%. The average for 1998-2004 was 21%.

CAPACITY/LOAD FACTORS

We are now including some output and load factor figures taken from Ofgem's data (lack of figures signals that a full year's production did not take place). This data is published in more accessible form by REF as a PDF download. (See 'UK Renewable Energy Data').

GLOSSARY

Scoping’ = site investigation, pre-application consultation with planning authority (may involve application to erect an anemometer mast for recording wind speeds, not required by the planning process but needed when raising finance).
Live Application’ = planning application submitted.
Appealed’ = proposals may be appealed by the applicant after refusal or for ‘non-determination’, when the applicant decides to trigger an appeal because the local planning authority has not determined the application within the prescribed time period (normally 12 weeks). Objectors have no right of appeal if a decision is approved, they can only seek to overturn the decision by going to the High Court (in England) to seek a judicial review of the decision on procedural grounds. This rarely succeeds and can be ruinously expensive if costs are awarded to the company.
Called in/Recovered’ = decision removed from a Planning Inspector to the Secretary of State, or Scottish equivalent. There are a number of reasons set out for this action, the English government has recently started recovering decisions because, “the appeal involves proposals of major significance for the delivery of the Government's climate change programme and energy policies.”
PI’ = Public Inquiry; hearing to publically examine the application in a quasi-judicial hearing before a Planning Inspector (‘Reporter’ in Scotland).
Status unclear’ = lapsed, withdrawn, not proceeding etc.
LF’ = Load Factor: percentage of headline capacity produced by turbine(s), averaged over a year.
NYD’ = Not yet determined.
TIGC’ = Total Installed Generating Capacity.

Rejected and lapsed/withdrawn proposals are included below because, even after failure at appeal, they can reappear as slightly adjusted re-submissions. Some developers are notoriousy unwilling to take no for an answer when they have spent some money in working up a proposal. These sites also indicate areas of developer interest.

Title colours match application status: orange - scoping/pre-planning; red - in planning (applied/appealed); green - approved; black - operating; grey - refused, withdrawn, lapsed etc.


QUICK NAVIGATION:


NORTH EAST ENGLAND


NORTHUMBERLAND


Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Aesica Pharmaceuticals Cramlington 2 110m. 2.5MW 5MW Refused.
Appeal withdrawn.
Applied 5/06 for two 140m turbines (06/00275/ful). Rejected 15.8.06, radar impacts
(Newcastle Airport).
Re-applied 8/06, two 110m turbines (06/00384/res). Permission refused. Appeal lodged, withdrawn before the hearing.
Barmoor Nr. Lowick
(NT980380)
6 110.5m. 3MW 18MW Catamount/
Force 9
Approved on appeal
Refused by LPA (27/03/08). Appeal heard (May-June 2009). Approved, on Inspector’s recommendation, 20/01/10.
SOUL.
‘Berwick’ ca. 1.5 km. N. of Halidon Hill 7 ?120m. 2MW 14MW RES
(not listed on website)
Scoping
Berwick - Ramparts Business Park Steps of Grace, north of Ramparts Business Park (NT 986555). 1 74m. 0.8MW 0.8MW Community Renewable Energy Ltd Scoping
Enercon E48 turbine proposed; 50m anemometer erected on the site in May 2008.
Income would be shared between Berwick Community Trust and CoRE.
'Bewick Drift' Lynemouth 3 110m. 3MW 9MW Harworth Power Approved on appeal (02/08)
Bewick Moor "2.9 km. SE of Chillingham" EHN UK Scoping
Mast (Dec. 2005)
Bewick Moor "3.8 km. NE of Old Bewick" EHN UK Scoping
Mast (Dec. 2005)
Blyth Harbour Blyth 9 42.5m. 0.3MW 2.7MW AMEC Operating (1993)
WindMaster turbines. Repowering, see below.

2002 ROC's/MWh:1,953
2003 ROC's/MWh:2,839; LF:12.0%
2004 ROC's/MWh:2,742; LF:11.6%
2005 ROC's/MWh:3,131; LF:13.2%
2006 ROC's/MWh:2,492; LF:10.5%
2007 ROC's/MWh:2,264; LF:9.6%
2008 ROC's/MWh:1,874; LF:7.9
Blyth Harbour
(Repowering)
Blyth 7 6 x 125m.
1 x 163m.
6 x 3MW
1 x 5MW
23MW Hainsford Energy Consented
(08.01.08)
An Article 14 hold on the decision pending a decision on whether to hold a PI on radar issues lifted July 2008.
5MW turbine would be largest in UK.
Blyth Offshore Nr. Blyth 2 93m. 2MW 4MW Project Consortium.
Sold to E.ON UK June 2007.
Commissioned 2000.
Inoperative 04.06 - 01.09
'Demonstration project' built with unspecified financial support from the EU Thermie Programme.
Blade accident on WTG 1, Jan. 2002.
ROC's only claimed on WTG 2. Out of service from April 2006 until January 2009 (cable damage).
2002 ROC's/MWh:1,925
2003 ROC's/MWh:2,557; LF:16.2%
2004 ROC's/MWh:4,181; LF:26.5%
2005 ROC's/MWh:1,385; LF:8.8%
2006 ROC's/MWh:337; LF:2.1%
2007 ROC's/MWh:0; LF:0%
2008 ROC's/MWh:0; LF:0%
Blyth Offshore 2 Nr. Blyth 1 163m. 7.5MW 7.5MW Crown Estates Scoping
Largest turbine proposed in UK.
Will use a ‘Project Britannia’ turbine, in development at Blyth.
Questions have been raised about engineering problems with CW’s onshore turbines, their lack of offshore engineering experience and poor financial performance.
It was recently reported (30 September, 2009) in The Telegraph that, “Clipper Windpower is in talks with industrial rivals and financial investors about selling a ‘substantial’ stake after making a $120m (£75m) half-year loss”. See also: The Times, 8 Nov. 2009.
Boundary Lane Nr. Whittonstall 3 110m 2MW 6MW Wind Prospect. Live application (16/06/2009)
Butterwell/Bluberry Wood
Nr. Longhirst 9 125m. 2.3MW 20.7MW RES, not on website Proposal announced.
Next to Novera’s Longhirst proposal.
Then LPA rejected Anem. Mast application (3/06), approved for 3 yrs.on appeal (12/06).
Coat Yards Farm Nr. Longhorsley 5 125m. 3MW 15MW Coronation Power 'Dropped after scoping' (NCC)
Currock Hill/Hedley-on-the-Hill Nr. Hedley-on-the-Hill 6
(2x3)
140m. ? ? Pure Renewable Energy Scoping
See Hexham Courant 25.01.08
Debdon Farm Nr. Rothbury 8 ? 3MW 24MW West Coast Energy Limited. Mast rejected.
Anem. Mast refused 8/07 (‘visually intrusive’).
Defra Headquarters, Alnwick Lion House, Alnwick 3 15m 0.15MW 0.45MW Operating
‘Defra’s green office’.
No (public) expense spared demonstration project, poor site for wind power generation. The achieved load factors will be worth seeing.
Gapshield Nr. Greenhead 5 ? 2.1MW 10.5MW RES
(not listed on website)
Scoping
Green Rigg Nr. Sweethope Lough 18 110m. 2MW 36MW Wind Prospect PI held
decision awaited
Joint public inquiry (+ Ray & Steadings) closed 18 Dec. 2008, decision awaited.
CREDIT - Campaign for Responsible Energy Development In Tynedale
Kielder Kielder Unclear
Still described as ‘strategic resource area’ in some circles.
Talks ongoing (?) with MOD on radar constraints.
Kielder
(Humble Hill)
Kielder (100) (80m.) (EcoGen) DTI (DBERR) Refusal
(MOD objected)
Upheld on jud. review.
Section 36 Application to DTI/DBERR (Over 50MW)
Originally seen as being in ‘Strategic resource area’.
Talks ongoing (?) with MOD on radar constraints. Also within the proposed exclusion zone for the Eskdalemuir seismological recording station (see maps).
Kiln Pit Hill Nr. Slaley 6 120m. 2MW 12MW NPower Consented on appeal
12/2/09
Inspector rejected Arup and listed buildings protection. See: Appeal Decision (PDF document).
Kirkharle Northside Farm & Bavington Hillhead, nr. Kirkharle 8(2x4) 125m. “up to 3MW” 18-24MW NPower Live Application
(18/11/2008).
Kirkheaton Kirkheaton, nr. Hexham 3 66.5m. 0.6MW 1.8MW EDF/Kirkheaton Wind Farms Commissioned 2000
Nordex turbines.Blades removed on 2 turbines due to faults; inoperative since Autumn 2008.
2002 ROC's/MWh:42,530
2003 ROC's/MWh:3,994; LF:25.3%
2004 ROC's/MWh:4,220; LF:26.8%
2005 ROC's/MWh:3,656; LF:23.2%
2006 ROC's/MWh:4,345; LF:27.6%
2007 ROC's/MWh:4,058; LF:25.7%
2008 ROC's/MWh:1,800; LF:16.7%
Lamb Hill Nr. Edlingham EHN UK Mast Rejected.
Mast Application Rejected by then LPA.
Not in ‘area of least constraint’.
Longhirst Nr. Longhirst 6 130m. “up to 2.5MW” 13MW Novera Proposal announced.
Next to RES’s Butterwell/Bluberry scheme.
www.noveraenergy.com
Contact: Dan Grierson, Project Director - 0131 243 1380.
Next to RES scheme.
Lynemouth Lynemouth 13 121.2m. 2MW 30MW CRE/Scottish Power Consented 01.09
Under construction.
MSD [Merck, Sharp & Dohme] Pharmaceuticals Cramlington 2 130m. 2.5MW 5MW Consented
(8/08).
Consented on appeal subject to effects on civil radar (Newcastle Airport) being ameliorated.
Middlemoor Nr. N. Charlton 18 125m. 3MW 54MW NPower Conditional consent
(8/8/08)
Approval conditional on solution to adverse effects on Air Defence Radar at RAF Brizlee Wood being implemented.
‘Moorsyde’ Shoresdean/Felkington
(NT934456)
7 110m. N/A N/A Your Energy
(Mistral)
Refused
Refused by LPA (27/03/08) against planners’ recommendation. Appeal heard (May-June 2009). Appeal rejected 20/01/10 by Secretary of State following Inspector’s recommendation.
Moorsyde Action Group.
Murton Murton 10 120m. 2MW 20MW RES
(not listed on website)
Scoping
Parkhead/Rayburn Lake Nr. Netherwitton 9 127m. 1.8MW 16.2MW RES. Live application
(28/8/09).
Plenmeller Nr. Haltwhistle 24 92m. 2MW 48MW Harworth Power (UK Coal) Scoping
Mast consented (01/07)
Northumberland County Council.
Not in 'area of least constraint'
Ray Estate 1. Nr. Kirkwhelpington 16 125m. 3MW 48MW Vattenfall PI held
decision awaited
Joint public inquiry (+ Ray & Steadings) closed 18 Dec. 2008, decision awaited.
CREDIT - Campaign for Responsible Energy Development In Tynedale
Project originated by AMEC Wind Energy Ltd. who have now sold off their wind interests. Acquired by Swedish company Vattenfall. See website page.
Ray Estate 2. Harwood Forest, Nr. Kirkwhelpington 22 120m. 3MW 66MW Vattenfall Scoping.
Anem. Mast approved.
CREDIT - Campaign for Responsible Energy Development In Tynedale.
Project originated by AMEC Wind Energy Ltd. who have now sold off their wind interests. Acquired by Swedish company Vattenfall. See website page.
Rimside Moor Nr. Rothbury 3 Rejected
(7/03)
Public Inquiry - rejected on landscape impacts.
Steadings (Plashetts) Nr. Kirkwhelpington 22 120m. 2-3MW 44-66MW Banks Developments PI held
decision awaited
Joint public inquiry (+ Ray & Steadings) closed 18 Dec. 2008, decision awaited.
CREDIT - Campaign for Responsible Energy Development In Tynedale
Thockrington Nr. Bavington 7 100m. 2MW 14MW Wind Prospect 'shelved' (15/07/06).
Scoping revised scheme.
Anem. Mast consented 2005.
Appears that Wind Prospect are reviving this proposal that was “shelved” in July 2006. Previously 14 x 100m. x 2MW. Details of new scheme not confirmed.
Local response group: CREDIT - Campaign for Responsible Energy Development In Tynedale.
Todburn East Longhorsley, 2km. 8 125m 3MW 24MW Coronation Power Proposal announced.
Anem. Mast appr. 7/06.
Todd Hill Between Pigden and Stanton.
4 101m. 2-2.5MW “8-10MW” Novera Live application (04/12/2008)
NCC Planning Ref. No. 09/00083/CCMEIA.
Novera contact: Dan Grierson, Project Director - 0131 243 1380.
Toft Hill Nr. Grindon/Shellacres
(NT906436)
7 112m. 2.7MW 19MW NPower Refused
Refused by LPA (27/03/08) following planners’ recommendation. Appeal heard (May-June 2009). Appeal rejected 20/01/10 by Secretary of State following Inspector’s recommendation.
Tone Hall W. of A68 Nr. Sweethope Lough 6 ? 2MW 12MW Nuon Renewables Scoping (02/02/2007)
Wandylaw Nr. N. Charlton 10 125m. 2-3MW 20-30MW Ridgewind Consented
Consented on appeal 10/2/09.
See: Appeal Decision (PDF document).
Wansbeck Hospital Ashington 1 43m. 0.1MW 0.1MW Inoperative
Vestas V20-100 turbine.
Shut down since 2007 due to blade damage (delamination).
Health trust have commissioned external report on repair/replacement.

1992 MWh:22.8; LF:N/A
1993 MWh:115.8; LF:13.2%
1994 MWh:162.3; LF:18.5%
1995 MWh:152.4; LF:17.3%
1996 MWh:151.3; LF:17.2%
1997 MWh:133.5; LF:15.2%
1998 MWh:122.6; LF:13.9%
1999 MWh:105.6; LF:12.0%
2000 MWh:129.3; LF:14.7%
2001 MWh:119.2; LF:13.6%
2002 MWh:128.1; LF:14.6%
2003 MWh:112.7; LF:12.8%
2004 MWh:79.8; LF:9.1%
2005 MWh:130.9; LF:14.9%
2006 MWh:126.1; LF:14.3%
2007 MWh:27.1; N/A
2008 MWh:0.0
2009 MWh:0.0
West Ancroft North Ancroft 8 115m 2.25MW “approx. 18MW” E.On UK. Live Application
(09/04/09).
West Moneylaws Nr. Mindrum, Cornhill. 6 125m. 3 18MW Coronation Power Abandoned
Abandoned after scoping (01/07)
Grid connection
Proximity Nat. Pk.
Whinney Hill Nr. Netherwitton ? 1??m. ?W ??MW Force9 Energy Scoping
Mast consented 07/03.
Wingates Wingates 6 110m 2 to 2.5MW 12 to 15MW Novera Energy Live application (Dec. 2008).
NCC. (A/2008/0604).
Consent for 70m mast (with lights) 26/2/09.
Local response group: Wingates NOT Wind Farms (WNWF).
Wingates Moor Nr. Wingates 4 100m 2.00-2.5MW 8 to 10MW BT Scoping.
NCC.
Split site, another 6 turbines proposed for East Wingates
Local response group: Wingates NOT Wind Farms (WNWF).
East Wingates Nr. Wingates 6 100m 2.00-2.5MW 12 to 15MW BT Scoping.
NCC.
Split site, another 4 turbines proposed for Wingates Moor
Local response group: Wingates NOT Wind Farms (WNWF).
UpbuttonBack to Quick Navigation

TYNE & WEAR


Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Eco Centre, Hebburn Hebburn 1 45.5m. 0.225MW 0.225MW Groundwork, South Tyneside Operating (8/05)
Single, small embedded turbine
First appears on register March 2007.
2006 ROC's/MWh:86
2007 ROC's/MWh:236; LF: 11.9%
2008 ROC's/MWh:233; LF: 11.8%
Nissan Sunderland 8 51m. 0.66MW MW Nissan Operating (11/05)
Small embedded turbines
SH Vestas V47.
2 more turbines consented in 2007.
Turbine fire December, 2005.

2005 ROC's/MWh:0
2006 ROC's/MWh:4,534
2007 ROC's/MWh:7,175; LF: 20.7%
2008 ROC's/MWh:8,559;
UpbuttonBack to Quick Navigation

COUNTY DURHAM


Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
‘A1’ “between Newton Aycliffe and Bradbury” 10 121m. 2-2.5MW 20-25MW E.ON UK Live Application
Barningham High Moor Nr. Barningham 25 54m. 15MW National Wind Power Refused
Refused locally and at appeal 1998. National Wind Power (NWP) failed in its attempt to persuade the High Court to overturn The Secretary of State's decision to refuse the grant of planning permission, 1999.
Broom Hill Nr. Tow Law
(NZ 159392)
4 102m. 2MW 8MW EDF Operating
(06/02/2009)
Ref. No. 3/2006/0087. Four REpower MM82 turbines. Causing TV problems for local residents, see Press.
Butterwick Moor Nr. Sedgefield 10 110m. 2-2.5MW 20-25MW E.ON.UK Consented (18/06/2007)
Immediately adjacent to Walkway scheme.
REpower has won the turbine contract (announced Dec. 2009).
‘Crake Scar’ Nr. Woodland 4 115m. 2MW 8MW Arcus
for Bolsterstone Innovative Energy (Woodland) Ltd.
Scoping
Contiguous with Windy Bank, see below.
Scoping Opinion available here. Scoping Report available here.
Edder Acres Nr. Shotton Colliery 2 11.2m. 2.3MW 4.6MW A7 Energy Refused
15/11/07
Re-submission refused
Refused 2005
Appeal refused.
Fox Cover Nr. Dawdon and Cold Hesledon, Seaham 2 125m. 3MW 6MW EDF Energy Refused
01/07/08
Just to N. of A182. Refused by Easington DC, then LPA.
Foxton Lane/Shotton Beck Heley House Farm, nr. Sedgefield 3 1??m. 2MW 6MW Wind Prospect Scoping
Anem. mast approved (7/09)- Appl. No. 7/2009/0239/DM. DCC Case Officer: David Walker.
Great Eppleton Nr. Hetton-le-Hole
(NZ 366 485)
4 69.5m. 0.75MW 3MW Powergen/E.ON.UK Shut down 2005. Repowering application 12/1/07 (see below).
4 x 69.5m 2-blade turbines (operating 1997-2004).

2002 ROC's/MWh:2,934
2003 ROC's/MWh:2,932; LF:11.2%
2004 ROC's/MWh:3,941; LF:15.0%
2005 ROC's/MWh:0; LF:0%
Great Eppleton Nr. Hetton-le-Hole
(NZ 366 485)
4 115m. 2MW 8MW E.ON.UK Consented
Repowering scheme.
REpower MM92 turbines.
The Greenhouse (Greencroft) Nr. Consett 1 43.5m. 0.225MW 0.225MW Groundwork w. Durham Operating 2006
Small embedded.

2006 ROC's/MWh:216;
2007 ROC's/MWh:286; [LF:14.5%]
2008 ROC's/MWh:203; [LF:10.2%]
[Ofgem changed TIGC from 225 to 97kW in mid 2006 after 5 months of operation. Reason is not clear. This then gives ludicrously high LF figures - our calculated figures are in brackets].
GSK Barnard Castle 2 45m. 0.25MW 0.5MW Glaxo Smith Kline Operating
Small embedded scheme
SH Micon turbines.

2004 ROC's/MWh:261; LF:N/A
2005 ROC's/MWh:389; LF:8.9%
2006 ROC's/MWh:359; LF:8.2%
2007 ROC's/MWh:441; LF:10.1%
2008 ROC's/MWh:414; LF: 9.5%
Hare Hill Nr. Peterlee
(NZ 371 414)
2 100m. 2.75MW 5.4MW Powergen/E.ON.UK Operating (2004)
NEG Micon NM80 turbines.

Hare Hill WTG 1 (2.314MW Cap.):
2004 ROC's/MWh:1,795; LF:N/A
2005 ROC's/MWh:3,732; LF:18.4%
2006 ROC's/MWh:4,305; LF:21.2%
2007 ROC's/MWh:4,305; LF:21.2%
2008 ROC's/MWh:5,649; LF:27.9%

Hare Hill WTG 2 (2.75MW Cap.):
2004 ROC's/MWh:1,625
2005 ROC's/MWh:3,510; LF:14.6%
2006 ROC's/MWh:3,898; LF:16.2%
2007 ROC's/MWh:5,279; LF:21.9%
2008 ROC's/MWh:4,104; LF:17.0%
Haswell Moor Nr. Haswell/Sherburn 5 110m. 2.3MW 11.5MW E.ON.UK Consented (01/08)

REpower has won the turbine contract (announced Dec. 2009).
Hawthorn West of A19, nr. Murton (NZ405460/NZ408463). 2 105m. 2.5MW 5MW SLP Energy Live application
Initial application April 2008, withdrawn September 2008. Resubmitted (Non-technical summary available).
High Haswell Nr. Haswell 2 100m. 2-2.5MW 4-5MW Hallam Land Management Consented (01/08)
High Hedley Hope Nr. Tow Law 3 71m. 0.75MW 2.25MW EDF/London Power Co. Operating (2002)
2002 ROC's/MWh:3,493
2003 ROC's/MWh:5,394; LF:27.4%
2004 ROC's/MWh:6,352; LF:32.2%
2005 ROC's/MWh:6,665; LF:33.8%
2006 ROC's/MWh:5,638; LF:28.6%
2007 ROC's/MWh:6,285; LF:31.9%
2008 ROC's/MWh:5,470; LF:27.8%
High Hedley Hope 2 Nr. Tow Law 4 105m. 1.3MW 5.2MW EDF/London Power Co. Operating
(10/08)
Nordex N60 turbines.
2008 ROC's/MWh:5,616;
High Sharpley Nr. Seaham. 2 90m. 1.3MW 2.6MW Cornwall Light & Power Company Ltd./REG Operating (2007)
See also refused extension at South Sharpley.
Nordex N60 turbines
2007 ROC's/MWh:5,379
2008 ROC's/MWh:6,476; LF:28.4%
High Volts Elwick, Hartlepool
(NZ 450 335)
3 100m. 2.75MW 8.1MW Powergen Operating (2004)
NEG Micon NM80 turbines.


High Volts 1 (2.314MW Cap.):
2004 ROC's/MWh:6,124; LF:30.1%
2005 ROC's/MWh:4,090; LF:20.1%
2006 ROC's/MWh:1,340; LF:6.6%
2007 ROC's/MWh:5,411; LF:26.6%
2008 ROC's/MWh:5,000; LF:24.6%

High Volts 2 (5.54MW Cap.):
2004 ROC's/MWh:6,970;
2005 ROC's/MWh:8,875; LF:18.4%
2006 ROC's/MWh:7,450; LF:15.5%
2007 ROC's/MWh:10,302; LF:21.4%
2008 ROC's/MWh:9,013; LF:18.7%
Holmside Nr. Stanley
(NZ 208 503)
2 100m. 2.75MW 5.5MW Powergen Operating (2004)
NEG Micon NM80 turbines.

Holmside WTG 1 (2.314MW Capacity):
2004 ROC's/MWh:2,584
2005 ROC's/MWh:4,040; LF:19.8%
2006 ROC's/MWh:3,300; LF:16.2%
2007 ROC's/MWh:5,306
2008 ROC's/MWh:4,663; LF:23.0%

Holmside WTG 2 (2.75MW Capacity):
2004 ROC's/MWh:2,184
2005 ROC's/MWh:4,596; LF:19.1%
2006 ROC's/MWh:3,431; LF:14.2%
2007 ROC's/MWh:4,042; LF:16.8%
2008 ROC's/MWh:3,219; LF:13.4%
INEOS Newton Aycliffe Ltd.
(Formerly Hydro Polymers).
Newton Aycliffe 2 48m. 0.25MW 0.5MW Hydro Polymers/TNEI “Project cancelled” (2008).
Small embedded scheme
Plastics plant.
Langley Nr. Burnhope
(NZ200 474)
4 102m. 2MW 8MW EDF Operating
REpower MM82 turbines.
Consented 6/05. Commissioned 13/08/2008.

2008 ROC's/MWh:4,921
Oakenshaw Nr. Oakenshaw 3 1??m. 2.75MW 8.25MW EDF Energy Pre-planning
Quarrington Hill Nr. Cassop 2 3MW 6MW Eco energy Refused (2004)
Appeal rejected
Sheraton Hill Nr. Wingates 3 3MW 9MW ? Unclear
Originated by United Utilities
Not listed by E.ON.UK who acquired UU's wind portfolio in 02/05.
South Sharpley Nr. Seaham, Co Durham 3 100m. 2.5MW 7.5MW Cornwall Light & Power Company Ltd./REG Refused
(22/12/2009)
Extension to existing scheme at High Sharpley.
Unanimous refusal following officer’s recommendation. Major reason: proximity to housing (450m).
Stanley Moss Nr. 2 107m. 2.3MW 4.6MW Amec/Banks Group Refused
(6/04)
Stobhill Nr. Bolam 7 Up to 125m. 2-2.5 MW 14-17.5MW NPower Announced
Tow Law Nr. Tow Law 3 71m. 0.77MW 2.31MW National Wind Power Operating
Nordex N50 turbines, commissioned 01/12/2001.

2002 ROC's/MWh:3,417
2003 ROC's/MWh:5,295; LF:26.2%
2004 ROC's/MWh:6,424; LF:31.7%
2005 ROC's/MWh:6,231; LF:30.8%
2006 ROC's/MWh:5,677; LF:28.1%
2007 ROC's/MWh:4,378; LF:21.6%
2008 ROC's/MWh:4,180; LF:20.7%
Trimdon Grange Nr. Trimdon 4 76m. 1.3MW 5.2MW EDF Operating
(10/07/2008)
Nordex N60 turbines.
Consented on appeal, 2005.

2008 ROC's/MWh:3,754
Walkway High Swainston
Nr. Sedgefield
7 110m. 2 14MW Wind Prospect Operating
(04/2008)
REpower MM82 turbines.
Immediately adjacent to Butterwick scheme. Operating as 2 entitities (Walkway 1 [R.O. ID R00197RQEN], 4 turbines & Walkway 2 [R.O. ID R00198RQEN], 3 turbines)

Walkway 1
2008 ROC's/MWh:7,200

Walkway 2
2008 ROC's/MWh:9,201
‘West Durham’ Nr. Satley/Tow Law 12 100m. 2MW 24MW Banks Developments
Operating
(5/09)
REpower MM82 turbines.
‘Windy Bank’ Nr. Woodland 5-9 115m. 2-3MW 10-27MW Banks Developments Scoping
Contiguous with Crake Scar (see above).
UpbuttonBack to Quick Navigation

TEES VALLEY


Hartlepool District

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Red Gap Farm Wolviston, Hartlepool 5 125m. 3MW 15MW BT Approved
(3/2/2010).

Middlesbrough District

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Middlesbrough Football Club Middlesbrough 1 90m 3MW 3MW Middlesbrough FC Approved
UpbuttonBack to Quick Navigation

Redcar & Cleveland District

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Teesside Offshore 1.5km off Coatham Sands, Redcar 30 ?140m. 2.5MW 75MW Northern Offshore Wind/EDF Consented 17.09.2007
Section 36 decision by BERR (DTI)
Redcar & Cleveland Co. may seek judicial review.
Teeswind North Corus steel site, Redcar 18 140m. 2.5MW 45MW AMEC Wind/Corus Consented (16.07.02 - R/2001/936/FF)
"In abeyance"
Tees Wind South Corus steel site, Redcar
(NZ 545 220)
10 140m. 2.5MW 25MW AMEC/Corus "In abeyance"

Stockton-on-Tees District

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Augean Landfill Site Port Clarence, Nr. Billingham. 4 126m. ? ? Augean PLC Scoping
Seamer Between Hilton and Seamer, nr. Yarm, on Stockton-on-Tees and N. Yorks boundary. 5 125m. “Up to 3MW” “Up to 15MW” Broadview Energy 3 consented, 2 refused.
Refused against recomm. by Stockton Borough Council (11/08) and Hambleton District Council [Yorkshire] (10/08).
Revised appl. approved on Chair's vote by SBC (3 turbines); HDC has refused the other 2 on 17/9/09 (7:5).
Article 14 hold on approval by the Government Office North East, the Secretary of State has now rejected a call-in (see press report,29 August 2009) .
SHWAG - Seamer & Hilton Windfarm Action Group
Stillington/Lamb's Hill Stillington, nr, Stockton 4-6 1??m. ?MW ?MW Banks Developments/Gaz de France Scoping
Project would include a small combined heat and power (CHP) plant on Stillington Industrial Estate.

Darlington District

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
East/West Newbiggin Nr. Sadberge, Darlington. 9 & 2 100m. ?MW ?MW Pure Renewable Energy, PB Power. project announced
2 adj. sites with 9 & 2 tubines.
Darlington Borough Council.
Moor House Nr. Barmpton, Darlington. 10 100 & 110m. 2-2.5MW 20-25MW Banks Developments Application
Banks Contact: Emily Hooson - 01740 658500 or e-mail: moorhouse@banksdevelopments.com
Application Reference: 09/00741/FUL.
Royal Oak Nr. Shildon 5 105m. 1.3MW 6.5MW EDF/Harworth Power (UK Coal). Consented (10/05)
UpbuttonBack to Quick Navigation

SOUTH EAST SCOTLAND


West Lothian

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Harrows Law Nr. Tarbrax 37 110m. 3MW 111MW Scottish and Southern Energy Pre-planning
Section 36 proposal (over 50MW)in Pentland Hills on the West Lothian/South Lanarkshire border. First submitted June 2005. “We are currently in the process of re-designing this proposal and hope to submit an application later this year.” (Website, June 2009.)
Pates Hill Nr. West Calder 7 107m. 2MW 14MW Your Energy Under construction.
Consented June 2007. project bought from ‘New Lives New Landscapes’. Adjacent to PM Renewables’ consented 15-turbine Tormywheel project, developed with Mistral/Your Energy, as at Drone Hill, Coldingham. Vestas V-80 turbines.
Tormeywheel Fauldhouse 15 102m. 2.75MW 41.25MW PI Renewables
(with Mistral)
Under construction.
Consented June 2007.
See appeal decision.
Near to other schemes at Black Hill (Lanarkshire) and Pates Hill (W Lothian).
UpbuttonBack to Quick Navigation

Midlothian

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Auchencorth Moss Nr. Penicuik
(NT210567)
14 102m. 2.5MW 35MW E.On UK Appealed
PI in progress.
Midlothian Council
Refused 11:3 following Officer's rec.
Appealed 27/08/08 - DPEA Appeal Ref. P/PPA/290/169.
Response Group: PEPA
Bowbeat extension Nr. Peebles 1 (5) 110m 2.3MW 9.2MW E.ON UK Scoping (2008)
4 turbines in Midlothian, 1 in Scottish Borders.

East Lothian

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Aikengall Nr. Innerwick
(NT694694)
16 125m. 3MW 48MW Community Windpower Ltd. Operational
(5/09).
Vestas V90 turbines.
Consented 13/03/07, against Officer's advice by Convenor’s casting vote.
Site in AGLV, SSSI within site.
Contiguous with Crystal Rig. Unlike CR, is very visible from the coast.
Aikengall II (‘Wester Dod’) Monynut Edge, Nr. Innerwick
(NT512676)
23 (30) “up to 145m” “up to 3.6MW” 82.8MW (108MW) Community Windpower Ltd. Live Application
23 in East Lothian, 7 in SBC area.
Section 36 application to Scottish Executive.
Twice the size of the original application!
Response group:
Save the Lammermuirs (STL).
Crystal Rig 2. (NT660690) 52 30x110m
22x125m.
128.8MW Natural Power Under construction.
Consented (01/05/04), 23 Turbines in Sc. Borders
29 in East Lothian.
Site in AGLV.
Crystal Rig 'Phase IIa' (NT678678) 9 125m. 3MW 27MW Natural Power Under construction.
Nos. Increase to Crystal Rig 2.
Site in AGLV.
Dunbar Cement Works Nr. Dunbar 3 125m. 3MW 9MW EDF Scoping
In 2008, Lafarge announced its intention to install three 125m wind turbines at its Dunbar Works. Four exhibitions were held on the company’s proposals, developed in conjunction with EDF Energy Renewables.
See PR statement.
Response group: Save the Lammermuirs (STL).
Keith Hill NE of Dun Law (Soutra) adj. to Pogbie 10 93.5m. 2-2.5MW 20-25MW Ron Shanks Development for G & M Hodge and Son. Live Application
Lammermuir Protection Group.
In AGLV.
Mast consented 7/08.
Pogbie Pogbie, Nr. Soutra Law 6 76m. 850kw (Vestas V52) 5.1MW Pogbie Farms, Agent: Natural Power Consented
(02/09/09)
Planning Ref. 08/00823/FUL.
East side of A68, Just north of Dun Law I/II.
Spott Roundabout A1, Layby E. Of Spott Roundabout, nr. Dunbar 1 32m. N/A N/A Community Wind Power "Application withdrawn"
Application withdrawn, 03/03/10.
UpbuttonBack to Quick Navigation

Scottish Borders

Name Place No. Height Max. MW Max. Capacity Developer Status Planning
Notes
Response Gp.
Aikengall II (‘Wester Dod’) Monynut Edge, Nr. Innerwick
(NT512676)
7 (30) 145m. “up to 3.6MW” 25.2MW (108MW) Community windpower Live application
7 of 30 turbines in SBC area.
Section 36 application to the Scottish Executive.
SBC Scoping opinion sought.
Response group: Save the Lammermuirs (STL).
Alemill Farm Nr. Eyemouth 8 ?m. ?MW ?MW ? Scoping
SBC Scoping opinion sought 06.06.07
Blackburn Blackburn Farm, nr. Grantshouse
(NGR 7866)
14 125m. ?MW ?MW Volkswind Scoping
Scoping approach confirmed by SBC (See press report).
Response group:
Save the Lammermuirs (STL).
Black Hill Nr. Duns
(NT735600)
22 78m. 1.3MW 28.6MW RES Operating (01/07)
Siemens turbines.
2006 ROC's/MWh:2,437
2007 ROC's/MWh:78,881
2008 ROC's/MWh:81,252; LF:32.4%
Blaewearie Nr. Clovenfords
(341 639)
“Up to 6 turbines” 1??m. ?MW ?MW Lomond Energy Pre-scoping
Scoping opinion requested from SBC, 07/10/10..
Border Precision Pinnacle Hill Ind. Est., Kelso 1 70m. 0.85MW 0.85MW Wind Direct Consented (02/08)
Refusal recommended by PO on grounds of visual impact.
Emly Bank (Bowbeat) Peebles
(NT285475)
12 76m. 1.3MW 15.6MW E.ON UK Operating (2001)
Appl. 00/00371/FUL, appr. 25/09/2000
Nordex N60 turbines.
2002 ROC's/MWh:11,061
2003 ROC's/MWh:32,602; LF:24.8%
2004 ROC's/MWh:35,862; LF:27.3%
2005 ROC's/MWh:36,474; LF:27.8%
2006 ROC's/MWh:34,600; LF:26.3%
2007 ROC's/MWh:35,197; LF:26.8%
2008 ROC's/MWh:37,085; LF:28.2%
Roughside Hill(Bowbeat) nr. Peebles
(NT285475)
12 76m. 1.3MW 15.6MW E.ON UK Operating
Appl. 00/00371/FUL, appr. 25/09/2000
Nordex N60 turbines.
2002 ROC's/MWh:10,361
2003 ROC's/MWh:33,539; LF:25.5%
2004 ROC's/MWh:35,987; LF:27.4%
2005 ROC's/MWh:37,736; LF:28.7%
2006 ROC's/MWh:35,860; LF:27.3%
2007 ROC's/MWh:39,354; LF:29.9%
2008 ROC's/MWh:38,633; LF:29.4%
Bowbeat Extension Nr. Eddleston (NT288473) 1 (5) 110m. 2.3MW 2.3MW (12.5MW) E.ON UK Scoping
1 turbine in SB. 4 in Midlothian.
Scoping opinion provided 01.08.08
Broadmeadows Yarrowford, nr. Selkirk
(NT410315)
13 112m. “between 2 and 3MW” 36MW Green Power Live Application
(23.12.04)
Appl. No. 04/02501/FUL
Broadmeadows Action Group
Brockholes Brockholes Farm, nr. Grantshouse
(NT815663)
3 84m. 0.9MW 2.7MW Green Cat Renewables
for Mr J Prentice
Live Application
(10.04.09)
Brotherstone Nr. Dun Law ?29 1??m. ?MW ?MW Ridgewind Pre-scoping
Pre-scoping meeting with SBC held (11/11/09).
Brunta Hill Nr. Westruther
(NT597514)
11 125m. 3MW 33MW Atmos Consulting Scoping
Scoping opinion requested from SBC 05/11/09, provided 21/12/09.
Response group: Save the Lammermuirs (STL).
Carcant Nr. Heriot
(NT362528)
3 107m. 3MW 9MW Airtricity Under construction.
SBC Appl. No. 05/01884/FUL. Airtricity, acquired from AMEC.
Consented (09.06)
Corbie Shank, Craik Forest Craik Forest, nr. Hawick
(NT337007)
73 N/A ca. 150MW REC Ltd. Scoping
SBC. Sect 36 scoping opinion provided 08.04.03
Crystal Rig - 'Phase 1'. (NT678678) 20 100m. 2.5MW 50MW Fred Olsen Renewables/
Natural Power
Operating (2003)
Appl 01/00269/FUL, appr. 10.09.01
Site in AGLV. Extension & C.R. Phase 2 consented, see below.

2003 ROC's/MWh:2,941
2004 ROC's/MWh:75,312; LF:17.2%
2005 ROC's/MWh:120,234; LF:27.5%
2006 ROC's/MWh:110,414; LF:25.2%
2007 ROC's/MWh:111,576; LF:25.5%
2008 ROC's/MWh:104,257; LF:23.8%
Crystal Rig - ‘Phase 1a’. (NT660690) 5 125m. 2.5MW 12.5MW Fred Olsen Renewables/
Natural Power
operational

Site in AGLV.
Crystal Rig - ‘Phase 2’. (NT678678) 23 (52) 30x110m
22x125m.
128.8MW Fred Olsen Renewables/
Natural Power
Under construction
Section 36 appl. 01.05.04, 23 Turbines in Sc. Borders
29 in East Lothian
.
Consented (01.05.04).Site in AGLV.
Crystal Rig - 'Phase 2a' (NT678678) 9 125m. 3MW 27MW Fred Olsen Renewables/
Natural Power
Under construction
Nos. Increase to Crystal Rig 2.
Site in AGLV.
Drone Hill/Coldingham Moor Nr. Coldingham (NT853685) 22 76m. 1.3MW 28.6MW PM Renewables: jt. venture by
PI Renewables/
Mistral Invest
Consented (11/08)
SBC Appl. No. 05/00425/FUL. Unanimous vote to follow officer's recommendation to refuse.
Consented on appeal, November 2008: Appeal Decision Notice.
Dunion Hill Nr. Denholm & Jedburgh
(NT615157)
8 101m. 2.3MW 18.4MW Windjen Power Refused at appeal.
Appl. No. 05/02336/FUL, 13.01.06. Refused SBC 10.09.07.
Refused on appeal 9.04.09 (first refusal on appeal for SBC). See Decision document.
Dunion Hill Conservation Group
Dun Law
[Soutra] .
Nr. Soutra
(NT460560)
26 67.5m. 0.66MW 17.16MW RES
for Sc. Power
Operational (2000)
RES for Scottish Power Renewables (owned by Iberdrola Renewables).
Appl. No. 96/01130/FUL. Appr. 31.07.97
Vestas V47 0.66MW turbines.

2002 ROC's/MWh:23,112
2003 ROC's/MWh:36,292; LF:24.1%
2004 ROC's/MWh:45,421; LF:30.2%
2005 ROC's/MWh:42,122; LF:28.0%
2006 ROC's/MWh:38,192; LF:25.4%
2007 ROC's/MWh:37,022; LF:24.6%
Dun Law 2.
(Soutra)
Nr. Soutra
(NT465575)
35 75m. 0.85MW 29.75MW RES
for Sc. Power
Operational
Appl. No.05/00847, consented 09/07. Vestas V52 turbines.
Scottish Power Renewables (owned by Iberdrola Renewables).
Earlshaugh Nr. Moffat
(NT080155)
36 125m. “Up to” 3MW “Up to” 108MW Wind Energy Ltd Live Application
PI now due.
Section 36 Application July 2008.
SBC objected (Nov. 2008).
Local response group: (SOS) Save Our Scenery
East Gordon Nr. Gordon ? ?m ? ? ? Pre-scoping.
SBC.
Fala Hill Nr. Heriot
(NT338655)
3 101m. 2.3MW 6.9MW E.ON.UK Refused
Appl. No. 04/02420/FUL.
Refused SBC 8/5/06.
Fallago Rig/Ridge Mk. II Nr. Longformacus
(NT570600)
48 100 & 125m. 3MW 144MW North British Windpower Live application
PI held.
PI to re-open.
Section 36 Application 16.05.05 (Mk. I).
Mk. II - numbers reduced from 62 (01/07).
SBC objection 05.02/07
PI held.
PI to re-open to rubber stamp approval after hearing new MOD radar evidence.
We now hear that the PI, under threat of legal action will hear all new evidence, not just radar (see Berwickshire News, 18 November 2009).
Response group:
Save the Lammermuirs (STL).
Frogden Farm Nr. Kelso 9 100m. 1.5MW 13.5MW Wind Hydrogen Ltd. Scoping.
SBC. “Scoping opinion sought 22.8.07”
Glenkerie (Kingledores) Nr. Tweedsmuir
(NT092279).
11 6 x 105m.
5 x 120m.
1.8-2.5MW 19.8-27.5MW Novera Consented
SBC appl. no. 07/02478/FUL. Consented SBC (08.09.08). Cleared for approval by SE 27.10.08.
Greenvale Craigswalls, Chirnside
(NGR 845 558)
1 c. 100m ? ? Greenvale Pre-scoping.
SBC. “Pre-scoping/pre-application submissions received 08.09.09”.
Halkburn (Long Park) Nr. Stow
(NT480420)
19 110m. 2MW 38MW Wind Prospect Operational
Appl. No. 04/00317/FUL.
Refused SBC (31/8/05)- landscape impacts.
Consented on appeal: Appeal Decision Notice.
REpower MM82 turbines.
Hawick Nr. Pilmuir, Hawick ? ?m. ? ?MW ? Pre-scoping
On Common Good Land near Williestruther Loch.
Proposed by ‘A Greener Hawick’ (see ‘Ill wind blows over turbine site proposal’, Hawick News, 11/02/2010).
Heathpool Nr. Eddleston
(NT255455)
6-7 ? ? Ridge Wind Pre-scoping.
SBC. “Pre-scoping opinion discussions, no scoping opinion requested”.
Hoprigshiels Nr. Oldhamstocks 5 125m ? Pre-scoping.
SBC.
Kinegar Quarry Nr. Cockburnspath
(NT376376 669840)
2 130m. 2.5MW 4MW) Kinegar quarry (S R Findlay).
Wind Direct
Pre-application.
SBC scoping opinion 13.07.09, anem. mast approved 06.05.09.
Nordex N100 turbines.
Response group: Save the Lammermuirs (STL).
Langhope Rig Nr. Ashkirk
(NT406203).
10 100m. 2.3MW 23MW Airtricity Consented.
SBC Appl. No. 06/01236FUL. Appl. Refused 07.07. Consented on appeal 05.08:
Appeal Decision Notice.
Hyndhope/W Alemoor
(Langhope Rig Extension)
Nr. Hyndhope. 10-15 125m. ?MW ?MW Natural Power Consultants Scoping.
SBC scoping opinion provided 24.02.09.
Leithope Nr. Carter Bar
(NT715095)
32 115m. 70MW Npower Scoping
SBC Sect 36 scoping opinion provided 22.12.05
Middle Hill Nr. Tweedsmuir 11 105m 2.45MW 27MW West Coast Energy Scoping.
SBC. Scoping opinion provided 12/09/05.
Minch Moor Nr. Innerleithen 12 100m. 2MW 24MW Vattenfall Live application
Local response group: Stop Minch Moor Windfarm.
Project originated by AMEC, sold to Swedish company Vattenfall. See website page.
Monashee Nr. Grantshouse (NT801611) 17 70m. 15MW West Coast Windfarms Unclear
SBC Scoping opinion 9/03.
Response group: Save the Lammermuirs (STL).
North Common, Selkirk Selkirk 6 125m. ?MW ?MW Selkirk Regeneration Group Scoping
SBC scoping opinion provided 24/06/09.
Map and other docs on Selkirk Community Council website.
Penmanshiel Moor Nr. Grantshouse
(NT822678)
19 125m. 2.5MW 47.5W RES Scoping
Scoping opinion sought from SBC 04/12/09.
Rowantree Nr. Fountainhall
(NT467500)
23 125m. 3MW 69MW RWE NPower Live application
(02/2010)
Section 57 application (over 50MW). Non-technical summary available free of charge from RWE NPower (Tel. 01738 825110)
Scoping document downloadable here.
Representions to Energy Consents at the Scottish Government or by email to energyconsents@scotland.gsi.gov.uk by not later than Monday 22 March 2010.
Sell Moor Nr. Oxton
(NT480444)
19 115m. 2.5MW 47.5MW RDC Refused
Appl. No. 04/00350/FUL. Refused SBC (31/8/05).
Toddleburn Action Group.
Spurlens Rig Nr. Leadburn
(NT248538).
5 125m. 2MW 12.5MW Lomond Energy Scoping
SBC scoping opinion provided 21/04/08 and 16/08/08.
APEAL - Association to Protect the Environment at Leadburn.
Standhill Nr. Denholm
(NT563233)
3 ?m ? ? Greenspan Agency Scoping.
SBC. Scoping opinion requested 08/09/09
Sunwick Nr. Hutton 5 145m 2MW 10MW RD Energy Solutions Pre-scoping.
SBC. “Screening request received 18 June 2009. Opinion provided 17 July 2009.”
Toddleburn Nr. Oxton
(NT450531)
12 110m. & 125m. 3MW 36MW Scottish & Southern Energy Operational.
Appl. No.04/01744/FUL. Refused SBC (31/8/05)- landscape impacts.
Consented (Jan. 07) on appeal: Appeal Decision Notice.
Upper Kidston Farm Nr. Peebles
(NT224424)
Max. 10 ? ? Volkswind Pre-scoping.
SBC. “Pre-scoping opinion discussions, no scoping opinion requested”.
Whitton Nr. Morebattle
(NT748207).
6 110m. “up to 3MW” up to 18MW Vattenfall Live application.
SBC Appl. No. 09/01162/FUL. You can comment online on the application.
Local response group: Protect Your Cheviots.
Project originated by AMEC, sold to Swedish company Vattenfall. See website page.
UpbuttonBack to Quick Navigation


NOTICE

Every effort has been taken to ensure that the information published on this web site is accurate. However, windbyte.co.uk can accept no liability for the accuracy of content which has been gathered from other published sources. Visitors who rely on this information do so entirely at their own risk.

If you find any errors - please email corrections to the webmaster.



Top  |   Home  |   Background  |   Single Map  |   North Map  |   South Map  |   SITE LISTINGS  |   Contact  |   Links  |  
Site design, graphics & photography:
Don Brownlow - Borders Photography